Structural Steel, Sewer Works and Stage 2 Advancements
Project:
Prime Business Park East Bendigo
Update:
13th June 2025
Milestone:
Panel Completion A1-A6
We’re pleased to provide you with a construction update from Prime Business Park East Bendigo, where momentum continues across multiple fronts of the development.
Structural Progress – Offices A1–A6
Following the successful erection of all precast concrete panels to Offices A1 through to A6, we’re pleased to report that structural steel installation is now well underway. Roofing steel is being lifted into place, forming the essential framework that will soon support roof sheeting and cladding.
In tandem, steel purlins have been delivered to site and are being staged for installation. Welding plates are also being fixed in position throughout A1–A6 in preparation for structural connections and framing works.
Civil Infrastructure Works
Underground infrastructure works continue across the broader site, with the main sewer installation program now actively progressing. These works form the backbone of essential services delivery for future tenancies and are being carried out in accordance with Coliban Water’s design and compliance standards.
Stage 2 Site Levelling & Bulk Earthworks
Stage 2 of the estate is taking further shape, with ongoing site levelling and bulk earthworks advancing steadily.
Foundation Works Complete – Warehouses G1, G2 & G3
We are pleased to confirm the successful completion of foundation works for Warehouses G1, G2, and G3. These factories represent the second phase of street-facing units within the estate and are a key component of Prime Business Park’s visual frontage. The upcoming erection of precast panels to G1, G2, and G3 will mark a significant milestone, bringing us closer to completing the estate’s prominent street façade.
With structural, civil, and earthworks all moving forward in parallel, the development team remains focused on maintaining program momentum and delivering a high-quality business precinct that supports long-term value for all stakeholders.
We look forward to keeping you informed with regular project updates as key milestones are reached throughout the construction journey.
Thank you for being part of this exciting development.
UPCOMING CONSTRUCTION WORKS:
Roofing steel to A1-A6
Concrete footings to G1-G3
Upgrading/replacement of authority services to site
Civil site works, cutting and levelling soil
Trenching works for warehouse services