Precast Concrete Panel Installations
Project:
M1 Business Park
Update:
29th Feb 2024
Milestone:
Precast Panel Installations
The latest phase of construction has witnessed significant advancements, particularly in the assembly of precast panels for warehouse units 26 to 33, as well as panel installations for units 24 and 25, which occurred today (Thursday, 29th Feb).
Notably, the slab foundation works for warehouses 22 and 23 have also been successfully completed, and concrete pours are scheduled to commence shortly.
The project has made substantial headway, with the development now visibly emerging from the ground and progressing seamlessly.
UPCOMING CONSTRUCTION WORKS:
Concrete slab pours to Warehouses 22 & 23
Installation of services to central warehouses
Installation of mains electrical pillar onsite
Preparation of foundations for Warehouses 01, 04 - 09.